Which jobs in Russia are done under a permit to work? The question sounds simple, and companies get it wrong constantly. Some lists cover only height and hot work; others forget loading operations or asbestos. The result is a gap in the paperwork, and when the labour inspectorate visits, an improvement notice and a fine. This page walks through all 24 categories of work done under a Russian permit. Each one is tied to Annex 2 of Ministry of Labour Order No. 776n of 29.10.2021 and to the industry rules that add requirements of their own.
If you need the legal thresholds that trigger a permit rather than the list of categories, they are covered separately in when a permit to work is required. What the document itself is and how the system works is explained in the overview of the Russian permit-to-work system.
Where does the number 24 come from?
A caveat before the table. Annex 2 to Order No. 776n lists 76 entries of high-risk work, and many of them describe the same hazard from different angles. We grouped those entries into 24 practical categories, folding in the industry rules: Order No. 903n for electrical work, Order No. 782n for height, FNP No. 528 for gas and hot work. Each category has its own crew requirements, safety measures and issuance procedure. The grouping is editorial, made to be readable. It is not a numbering taken from the act itself.
The legal status of the baseline list matters more than its count. The Annex 2 list is indicative. Every company must approve its own list, adapted to what it does, under Government Decree No. 2464. A petrochemical plant and a housing-services firm will end up with very different lists; only the core will match.
Permit, work order or routine operation?
Not every hazardous job needs a full permit. Russian occupational safety rules recognise three forms of organising work, and the permit to work is the strictest.
Under a permit to work run the highest-risk jobs from the company list: a written authorisation with the location, time, crew, responsible persons and specific safety measures. That is the 24 categories in the table below.
Under a work order run jobs of lower risk, on a written or oral instruction of a manager, without the full permit package.
As routine operation run simple recurring tasks from a pre-approved list, with no separate authorisation for each.
The form is chosen by the governing act and the company list, never by the worker on the spot. If a job is on the high-risk list and no lighter form has been formally set for it, the default is a permit to work.
The full table: 24 categories of permit work
| # | Category | Main legal basis | Where it is most common |
|---|---|---|---|
| 1 | Excavation | Order No. 776n (Annex 2, pos. 1) | Construction, utilities, oil and gas |
| 2 | Repair, installation, dismantling | Order No. 776n (Annex 2, pos. 2) | All industries |
| 3 | Hot work | Order No. 776n; FNP No. 528 | Oil and gas, metallurgy, utilities |
| 4 | Work at height | Order No. 776n; Order No. 782n | Construction, power, telecoms |
| 5 | Gas-hazardous work | FNP No. 528 | Oil and gas, chemicals, utilities |
| 6 | Confined and enclosed spaces | Order No. 776n; FNP for hazardous facilities | Oil and gas, utilities, shipbuilding |
| 7 | Electrical installations | Order No. 903n | Power industry, manufacturing |
| 8 | Lifting operations | Order No. 776n; FNP for lifting structures | Construction, ports, warehouses |
| 9 | Blasting | FNP, Rostekhnadzor Order No. 494 | Mining, tunnelling |
| 10 | Radiation sources | NRB-99/2009; OSPORB-99/2010 | Weld inspection, nuclear industry |
| 11 | Hazardous chemicals | FNP for hazardous facilities; Order No. 776n | Chemicals, oil and gas, water utilities |
| 12 | Diving | Industry safety rules | Hydraulic works, ship repair |
| 13 | Pressure pipelines | FNP for pressure equipment; Order No. 776n | Power, oil and gas, utilities |
| 14 | Logging | Ministry of Labour Order No. 644n | Forestry |
| 15 | Work in traffic zones | Order No. 776n; industry rules | Rail, roads, ports |
| 16 | Demolition | Order No. 776n; SP 325.1325800 | Construction, redevelopment |
| 17 | Extreme temperatures | Labour Code Art. 109; Order No. 776n | Metallurgy, the Far North |
| 18 | Cleaning and painting | Order No. 776n | Shipbuilding, manufacturing |
| 19 | Gas-supply facilities | FNP; Government Decree No. 410 | Gas networks, utilities |
| 20 | Pressure vessels | FNP for pressure equipment (Order No. 536) | Chemicals, power, food industry |
| 21 | Nuclear facilities | Federal Law No. 170-FZ; OSPORB-99/2010 | Nuclear industry |
| 22 | Loading and unloading | Order No. 776n | Logistics, ports, warehouses |
| 23 | Power-line protection zones | Order No. 903n; Decree No. 160 | Construction, power industry |
| 24 | Asbestos-containing materials | SanPiN 1.2.3685-21 | Demolition, roof repair |
Each row has sub-types. The repair category alone (No. 2) covers dozens, from dismantling structures to work near open moving machinery. In practice almost any repair at an industrial site lands in it.
Construction, excavation and demolition
Three rows (1, 2, 16) share one hazard type: physical impact on structures, soil and buried services.
Excavation needs a permit when the excavation site is close to buried services such as gas pipes, cables or water mains, in pits deeper than 1.5 metres, or in ground with pathogenic contamination. The classic incident: a contractor starts a trench for a fence footing inside a plant and cuts a 10 kV cable that nobody told him about. Without a permit and the owner's sign-off, that story repeats every year.
Repair, installation and dismantling is the broadest category: equipment installation, work near open moving parts, repair of steam and hot-water lines, temporary welding during repairs. Demolition stands separately because its focus is unstable structures: taking down damaged buildings, breaking foundations, shoring up emergency structures.
Hot work, gas-hazardous work and confined spaces
Rows 3, 5 and 6 overlap constantly in real plants. A welder working inside a tank is doing hot work, in a confined space, and if the tank held petroleum products, in a gas-hazardous atmosphere, all at once. Whether that takes one permit or three depends on the company's own procedures; in oil and gas the hot-work permit is usually issued separately.
Hot work covers electric and gas welding, cutting, brazing and bitumen heating. Gas-hazardous work is any job in an atmosphere where harmful gases or vapours may appear: tie-ins to live gas pipelines, leak testing, work in vessels and manholes; the procedure is set by FNP No. 528 and covered in detail in the article on gas-hazardous work permits. Confined spaces mean tanks, bunkers, boiler fireboxes, manifolds, tunnels, sewage manholes and pits deeper than 1.5 metres; utilities record fatal incidents in manholes every year, usually from methane or hydrogen sulphide.
Height and electrical installations
Work at height (row 4) is one of the most common permit categories: steeplejack work above 5 metres, any work above 1.8 metres without guard rails, roofs, masts, power-line towers, suspended cradles. The rules are in Order No. 782n, and the full system is described in the guide to work at height.
Electrical work (row 7) runs under Order No. 903n, covering installations up to and above 1000 V: switchgear, overhead and cable lines, substations. Crew members need electrical safety groups II to V depending on the role. The procedure, including who signs and who admits, is in the article on electrical work permits.
Pressure equipment and lifting
Lifting operations (row 8) cover cranes, hoists, lifts, conveyors and rigging of heavy loads. Pressure pipelines (row 13) mean repair of steam lines, pressure testing and hot tie-ins. Pressure vessels (row 20) cover internal inspection and repair of autoclaves and reactors, and cleaning of vessels that held hazardous substances. Loading and unloading (row 22) becomes permit work when the load is heavy, oversized or dangerous; the focus is the cargo, where row 8 focuses on the machine.
The special ten: from blasting to asbestos
The remaining categories are narrower but no lighter. Three belong to the world of major industrial hazards. Blasting (row 9) lives in mining and tunnelling. Radiation sources (row 10) mean gamma inspection of welds and the handling of radioactive substances. Hazardous chemicals (row 11) bring in chlorine, ammonia, acids and alkalis, which is what puts water utilities with chlorination plants on the list. Diving (row 12) is the narrowest of all, and logging (row 14) has a Ministry of Labour order of its own.
A second cluster is defined by the environment rather than the substance. Work in traffic zones (row 15) covers rail tracks, roads, ports and airfields. Extreme temperatures (row 17) apply outdoors below minus 25 or above plus 35 Celsius, and in hot shops. Cleaning and painting (row 18) usually rides together with confined spaces. Gas-supply facilities (row 19) bring tie-ins, gas start-up and regulator stations.
The last three rows carry the strictest oversight. Nuclear facilities (row 21) run under Federal Law No. 170-FZ, with the operator's own procedures supervised by Rostekhnadzor. Power-line protection zones (row 23) catch cranes and excavation near overhead lines. And asbestos (row 24) surfaces in almost any renovation of a Soviet-era building, because the material was used everywhere.
How do you classify a real job?
In practice, classifying a specific task is harder than memorising the table. The working algorithm has four steps.
- Describe the job in one sentence: "repair of a heat exchanger inside a column at a refinery".
- Check the table for matching rows. In the example: row 2 (repair), row 6 (confined space), row 3 if welding is needed, row 5 if hydrocarbon residues are possible.
- Open the company's approved list of high-risk work and check the job is on it. If the list does not exist, that is a violation on its own.
- Decide how many permits the job needs, one combined or several separate. That decision belongs to the person issuing the permit together with the responsible manager.
If the job matches no row at all, it may run without a permit. When in doubt, issue one anyway: the penalty for a missing permit costs more than the hour spent preparing it.
How does this list look to a foreign contractor?
International companies fall into two traps here. One is mapping. A global contractor arrives with its own PTW matrix, typically five or six permit types: hot work, confined space, working at height, electrical, excavation, sometimes lifting. The Russian company list is longer and legally binding, so a job that needs no permit under the corporate matrix, say asbestos removal or work in a power-line protection zone, may be permit work at the Russian site. The site's approved list wins, because inspectors check against it, not against corporate standards.
The other trap is where the obligation lives. Under HSG250-style guidance in the UK, the permit system is the operator's own control measure; in the US, OSHA mandates permits for specific hazards such as confined-space entry. In Russia the trigger is the employer's approved list built on Annex 2 of Order No. 776n, a document with legal force. A missing list is itself a recordable violation, before a single job starts. In my supervision practice the first document a foreign contractor should request from a Russian client is exactly that list, in its current approved version.
What happens if the permit is skipped?
The labour inspectorate treats work from the high-risk list done without a permit as a breach of occupational safety requirements. The base penalty under Article 5.27.1 of the Code of Administrative Offences is a fine of 50,000 to 80,000 RUB (about 590 to 950 US dollars) for the company. Specific offences under parts 2 to 4, from a missing assessment of working conditions to missing protective equipment, run 60,000 to 150,000 RUB (about 710 to 1,775 dollars), and a repeat violation under part 5 reaches 100,000 to 200,000 RUB (about 1,180 to 2,370 dollars) or suspension of operations for up to 90 days. If the missing permit contributed to an accident, the case moves to Article 143 of the Criminal Code, up to imprisonment of the responsible person. The full breakdown by site type and repeat offences, including hazardous production facilities, is in penalties for working without a permit.
The inspector also records the side violations: no approved list, no target briefing, no appointed responsible persons. Each goes into the notice as a separate item.
Frequently Asked Questions
Are all 24 categories mandatory for every company?
No. The list in Annex 2 to Order No. 776n is indicative. Each organisation draws up its own list to match its operations. An office company may have none of the categories; an oil refinery will typically carry 15 to 18 of the 24.
Can several types of work go on one permit?
It depends on the company's own procedures. Where repair work and welding run at one location with one crew, some companies allow a single permit that lists all the safety measures. In oil and gas, hot work usually gets its own separate permit, whatever else is on site.
What if a job does not fall into any of the 24 categories?
Then it may run without a permit to work, under a work order or as routine operation of listed recurring tasks. If there is any doubt, issuing a permit is the safer choice: the liability for a missing document is far heavier than the time spent preparing one.
Who approves the list of high-risk work at a company?
The employer or an authorised person, usually the technical director or chief engineer. The legal basis is Government Decree No. 2464 of 24.12.2021, and the list is approved by an order for the organisation.
Is a written list of high-risk work mandatory?
Yes. The employer approves it by order, building on the baseline in Annex 2 to Order No. 776n and the company's own operations. Without such a list the labour inspectorate records a separate violation, even when the individual permits themselves are in order.
How long is a permit valid for each category?
It depends on the governing act. The general rule is the period of the task. Hot work at a hazardous facility runs one shift per permit under FNP No. 528. Electrical permits run up to 15 calendar days under Order No. 903n. The full table by category is in the validity-period article.
Sources
- Ministry of Labour Order No. 776n of 29.10.2021 (Model regulation on the occupational safety management system; Annex 2, indicative list of high-risk work)
- Rostekhnadzor Order No. 528 of 15.12.2020 (FNP "Rules for the safe conduct of gas-hazardous, hot and repair work")
- Ministry of Labour Order No. 903n of 15.12.2020 (Occupational safety rules for the operation of electrical installations)
- Ministry of Labour Order No. 782n of 16.11.2020 (Occupational safety rules for work at height)
- Government Decree No. 2464 of 24.12.2021 (Procedure for occupational safety training and knowledge testing)
- Article 5.27.1 of the Code of Administrative Offences (breach of state occupational safety requirements)
- Article 143 of the Criminal Code of the Russian Federation (violation of occupational safety requirements)